Hearing and Accompanied Site Visits

Appeal reference Appellant(s) Development Location Date and time of hearing or site visit Hearing/Site Visit Location Appointed commissioner
2025/A0092 McBride, James Demolition of listed Mill Buildings with part retention of Buildings 2a and 2c adjacent to Mill Street Hilden Mill Bridge Street, Hilden, Lisburn, BT27 4RZ Tuesday, 03 March 2026 10:30 Appeal Site - Hilden Mill, Bridge Street, Hilden, Lisburn, BT27 4RZ Kevin Gillespie
2025/L0009 Cleland, Crosby Application seeking confirmation of lawful commencement of development under planning reference's R/2003/0583/O and R/2006/0946/RM by way of the excavation and pouring of foundations within required time limits 150m North of, 32 Greens Road, Saintfield, BT24 7EE Tuesday, 03 March 2026 10:30 Appeal Site-150m North of, 32 Greens Road, Saintfield, BT24 7EE Gareth McCallion
2025/E0048 Dalradian Gold Limited Alleged (1) Failure to comply with condition 5 of K/2014/0387/F in that site decommissioning has not been carried out in accordance with the approved Site Decommissioning Method Statement (Appendix 2) in the following respects: (i) Removal of explosives store building and concrete slab, access track extension and hardstanding in accordance with the approved details and timescale has not been carried out; (ii) Removal of temporary protective fencing gates and CCTV in accordance with the approved details and timescale has not been carried out; (iii) Removal of temporary protective housing around existing ventilation raise in accordance with the approved details and timescale has not been carried out; (iv) Removal of culverts and headwalls in accordance with the approved details and timescale has not been carried out. (2) Failure to comply with condition 6 of K/2014/0387/F in that the implementation of the site restoration in accordance with conditions 5 and 7 has not been completed within the timeframe stipulated Lands approx. 600m southwest of No 45 Camcosy Road, Curraghinalt, Gortin, Co. Tyrone, BT79 7SF Wednesday, 11 March 2026 10:30 PACWAC 4th Floor 92 Ann Street Belfast Trudy Harbinson
2025/E0049 Dalradian Gold Limited Alleged (1) Failure to comply with condition 39 of K/2014/0246/F in that site decommissioning has not been carried out in accordance with the approved Site Decommissioning Method Statement (Appendix 2) in the following respects: (i) Removal of office/welfare containers in accordance with the approved details and timescale has not been carried out; (ii) Removal of warehouse buildings in accordance with the approved details and timescale has not been carried out; (iii) Removal of building foundations in accordance with the approved details and timescale has not been carried out; (iv) Removal of the water treatment plant in accordance with the approved details and timescale has not been carried out; (v) Removal of yard area hardstanding in accordance with the approved details and timescale has not been carried out; (vi) Removal of berms in accordance with the approved details and timescale has not been carried out; (vii) Removal of security hut in accordance with the approved details and timescale has not been carried out; (viii) Removal of perimeter/security fencing, gates and CCTV in accordance with the approved details and timescale has not been carried out. (2) Failure to comply with condition 40 of K/2014/0246/F in that site restoration has not been carried out in accordance with the approved Restoration Method Statement (Appendix 3) in the following respects: (i) Removal of office/welfare containers in accordance with the approved details and timescale has not been carried out; (ii) Removal of warehouse buildings in accordance with the approved details and timescale has not been carried out; (iii) Removal of building foundations in accordance with the approved details and timescale has not been carried out; (iv) Removal of the water treatment plant in accordance with the approved details and timescale has not been carried out; (v) Removal of yard area hardstanding in accordance with the approved details and timescale has not been carried out; (vi) Removal of berms in accordance with the approved details and timescale has not been carried out; (vii) Removal of security hut in accordance with the approved details and timescale has not been carried out; (viii) Removal of perimeter/security fencing, gates and CCTV in accordance with the approved details and timescale has not been carried out. (3) Failure to comply with condition 41 of K/2014/0246/F in that the implementation of the restoration of the site in accordance with Drawing Number 14 (approved under K/2013/0072/F) (Appendix 4) and in accordance with conditions numbered 39 and 40 of K/2014/0246/F was not completed on or before three years from the date of commencement Lands approx. 165m west of 45 Camcosy Road, Curraghinalt, Gortin Wednesday, 11 March 2026 10:30 PACWAC 4th Floor 92 Ann Street Belfast Trudy Harbinson
2025/E0061 Castlerock Presbyterian Church Alleged (a) Unauthorised extensions to caravan, being developed without the necessary grant of planning permission required Land at 661 Seacoast Road, Limavady, BT49 0LH Thursday, 12 March 2026 10:30 PACWAC 4th Floor 92 Ann Street Belfast Carrie McDonagh
2025/E0062 Wilson, Robin Alleged (a) Unauthorised extensions to caravan, being developed without the necessary grant of planning permission required Land at 661 Seacoast Road, Limavady, BT49 0LH Thursday, 12 March 2026 10:30 PACWAC 4th Floor 92 Ann Street Belfast Carrie McDonagh
2025/W0001 Mairs, Raymond Fish Culture Licence subject to conditions for operating a fish farm at Loughinsholin Fisheries - Addition of Atlantic Salmon (Salmo salar) as a licenced species 12b Portna Road, Kilrea, Co Londonderry, BT51 5SW Monday, 16 March 2026 10:30 PACWAC 4th Floor 92 Ann Street Belfast Beverley Stevenson